BANGALORE: Metro can only blame itself for the delays. Even if the private contrators delay, the Bangalore Metro Rail Corporation ..
BANGALORE: Metro can only blame itself for the delays. Even if the private contrators delay, the Bangalore Metro Rail Corporation Limited (BMRCL) can take no action.
Recently on Reach 3, the Noidabased company ERA was shunted out for delay in the work but a similar stance cannot be adopted with contractors on Reach 1. The reason in the first place BMRCL could not start the project on time.A private contractor, who did not wish to be named, said that they were ready to begin work in early 2007, but the BMRCL had not even prepared the drawings till the end of that year and even after one year, the company had provided only 80 per cent of the total land required for the stretch.